Get that IT project back on track

As a consultant, one of the things I am often asked to do are project reviews: when things have not gone well, the stakeholders are looking for recommendations to get their project back on track. When projects get into trouble it is often for one (or more) of the following reasons:

Lack of a clear vision or business case

We don’t know what we don’t know

Scheduling without specs and late changes to specs

Schedules based on desire, not reality

Inadequate resources

Cross-product dependencies

Vendor dependencies

Inadequate tools

Lack of a Clear Vision

Bright ideas alone are not enough for project success. The project’s business case should reflect a compelling, understood, and agreed- upon business need. Think about the number of projects you’ve seen that have begun as nothing more than a verbal request with little or no analysis behind it. The project vision (or charter) should articulate why the project is being undertaken and explicitly note what the organization expects to achieve, the rationale for any deadline, who the target customers are, who the competitors are within that market, and what is and is not going to be included in the scope of the project. If this foundational material cannot be articulated in one to two pages, the project will be under a cloud of uncertainty from the beginning. However, the project team will go forward with enthusiasm and will compensate for the uncertainty by making assumptions that often go untested until it’s too late.

We Don’t Know What We Don’t Know

This is especially true in new product development. The problem occurs when we don’t admit that there may be key areas of knowledge, business climate factors, and other important items, about which we don’t know. And to preserve our egos, we lead stakeholders to believe we know what we’re talking about. One way to accommodate uncertainty that is inherently unknowable is to adopt a feature-driven development (FDD) approach. By producing a very preliminary functional spec at the beginning, with the most important features being detailed and developed in the earlier iterations of development, FDD allows the project team to adapt as better information becomes available. FDD couples with risk management and schedule buffer to allow teams to make mid-course corrections while managing stakeholder expectations.

Scheduling Without Specs and Late Changes to Specs

These are really one in the same problem. Schedules without specifications are pure fantasy. A project schedule reflects the work to be done as outlined in the specification. Specifications always drive the schedule, not the other way around. When I see a lot of late changes to a spec, that usually indicates that not much time was spent on the spec and what looks like “changes” are really the spec being created. Specs are often compromised in order to get developers working on the product. The spec serves as an implementation guide for development and test. At a minimum, the development iteration at hand should have a clear spec to guide the work of the developers and testers.

Schedules Based on Desire Too often when a project is begun, the only thing known is the deadline. The definition of the rest of what is to be done is pretty much content free. While there is nothing inherently wrong with an aggressive release date, it must also be realistic. The time to talk with stakeholders (usually marketing) about unrealistic deadlines is after the team has had time to assess what can and cannot be accomplished. And this means after some preliminary spec and schedule development has been done. It is much more helpful to tell stakeholders what they can have and by when than to commit to a fantasy project doomed to failure.

Inadequate Resources

Organizations, like individuals, do not function well under extreme schedule pressure. One of the ways this manifests itself in organizations is in assigning the same individuals to multiple priority-one projects. Using the shared resource approach, instead of getting the most important project completed and out the door first, that project is doomed to be completed at the same time (or later) than the least important project. Remember, there can only be one “priority one” project.

Cross-Product Dependencies

At a strategic level, it makes economic sense to utilize products, or their components, that are being developed by different teams within the organization. Why should each group reinvent (reinvest) the wheel? Unfortunately this is easily said and hard to implement. Product groups usually have different release schedules, different target customers, different competitive demands, and when asked to deliver a product internally for use, guess what the lowest priority is for that group? That’s right: delivering the product for internal use, especially if that need is seen as financially less important to the organization than the external demands. Many things are required to allow cross-product work to operate more smoothly, but fundamentally, management must set cross-group priorities and ensure that rewards are consistent across efforts to complete internal and external products.

Vendor Dependencies

Have you ever experienced vendors not delivering on time, not delivering what was specified, and bringing their technical leads to the initial meeting then staffing the project with less experienced staff? Why would responsible vendors do this?

Often it’s because there is no compelling legal reason to do otherwise. Take a look at your contract. Have you specifically stated your review and acceptance authority regarding the initial and subsequent vendor staff? The same due diligence should be spent finding and qualifying vendors as what the organization spends in recruiting and hiring full-time staff. And that includes the contract. Too often, in the rush to bring a vendor on board, little time is spent putting the specs into the contract and defining the terms of that business relationship. To avoid later difficulties, spend time specifying the deliverables, defining unambiguous acceptance criteria, determining how and when payment is to be made, stating your review and acceptance authority over interim and the final product, and vendor requirements for correcting errors to the product after release. While a meeting of the minds is key to a productive vendor relationship, you need to get it in writing.

Inadequate Tools

Don’t get me wrong, it’s rarely all a “tool problem,” but trying to develop a product with tools that are also under development is very difficult. If new technologies and nonexistent tools are a requirement for the release, your back-up plan should include a release with the old toolset or make sure the tool developers are part of your project team.

It’s a “pay me now or pay me a lot more later” issue. If you make the investment of time and effort to create a well-defined project at the outset, you won’t be spending time killing the project later, and most important, you won’t be writing off the money you invested in a “doomed-to-fail” project.

— Lynne Nix, Senior Consultant, Cutter Consortium

Would you recommend this article?

Share

Thanks for taking the time to let us know what you think of this article!
We'd love to hear your opinion about this or any other story you read in our publication.


Jim Love, Chief Content Officer, IT World Canada

Featured Download

Featured Articles

Cybersecurity in 2024: Priorities and challenges for Canadian organizations 

By Derek Manky As predictions for 2024 point to the continued expansion...

Survey shows generative AI is a top priority for Canadian corporate leaders.

Leaders are devoting significant budget to generative AI for 2024 Canadian corporate...

Related Tech News

Tech Jobs

Our experienced team of journalists and bloggers bring you engaging in-depth interviews, videos and content targeted to IT professionals and line-of-business executives.

Tech Companies Hiring Right Now